They are narrowing up the creek crossing, logging the sides,hardpanning it. Just trying to protect it as much as possable.
They are also going to close the same creek crossing under the powerlines, and redirect traffic down the main road and over to the power lines.
So, depending on equipment and I will discuss this with charlie tommorow night. Here is the rough plan.
We need rock dumped up on the upper road to the new area.
The creek crossing has to be closed under the power lines and the creek crossing on the road finished.
I am not sure what will be done by satuday with the equipment that the DNR has now.. Hopefully have more answers to this at the meeting tommorow night...
As for which day. I would say saturday...