Hi all,

The meeting this week on Wednesday will cover items like:

* David Way's replacement at Reiter;

* Revised 4x4 trail designs;

* Construction updates.

If you have opinions about the design of 4x4 trails at Reiter Foothills you should attend this meeting!

-Alan
 
New David is Ben
G-11 trail plans are 100% drawn
t&t plans are 75% completed
DNR has not hire the second equipment operator but they have some interviews setup. But it sounded like the current operator is very actively looking for a full time spot so we may loss him before the trails are completed...

Material(s) for the G11 and T&T will start to get ordered this week at least all the trail bed material.

The one motorcycle trail is about 50% completed, when completed the WCC crews will move over to the upper part of the trunk trail.

The non-motorized the bridge contract has been rewarded sounds like construction will start like in September-ish but may not open until next spring-ish...

Talked about maintenance needs in the 4x4 area.
 