New David is Ben
G-11 trail plans are 100% drawn
t&t plans are 75% completed
DNR has not hire the second equipment operator but they have some interviews setup. But it sounded like the current operator is very actively looking for a full time spot so we may loss him before the trails are completed...
Material(s) for the G11 and T&T will start to get ordered this week at least all the trail bed material.
The one motorcycle trail is about 50% completed, when completed the WCC crews will move over to the upper part of the trunk trail.
The non-motorized the bridge contract has been rewarded sounds like construction will start like in September-ish but may not open until next spring-ish...
Talked about maintenance needs in the 4x4 area.